|
Idaho Cleanup Project completes work at Test Area North complex at DOE’s Idaho site
 |
|
Loss-Of-Fluid Test Reactor Facility (before) |
|
|
Idaho Cleanup Project workers have completed all the original contract work
scope at the U.S. Department of Energy’s Idaho Site’s Test Area North (TAN)
complex. The work involved close cooperation among the Department of Energy, the
Environmental Protection Agency and the Idaho Department of Environmental
Quality, with public input incorporated into end-state decisions at numerous
stages along the way. The work included demolition of nuclear facilities, an old
reactor containment building and thousands of square feet of support buildings,
other structures, and many underground tanks and lines. It was completed four
years ahead of schedule and well under budget.
Completing the cleanup work at the Test Area North complex removed more than
270,000 square feet from the footprint of DOE Environmental Management-owned
facilities at the Idaho site. The funds that would have been used to maintain
the unneeded or obsolete facilities were redirected to other cleanup work at the
Site. Although the originally planned work at TAN has been completed, under the
recent American Recovery and Reinvestment Act, an additional small-scale soil
cleanup has been added to the schedule and will be completed later this summer.
 |
|
Loss-Of-Fluid Test Reactor Facility
(after) |
|
|
The TAN facilities were largely constructed between 1954 and 1961 to support
the Aircraft Nuclear Propulsion Project of the U.S. Air Force and the Atomic
Energy Commission. Upon termination of this research, TAN structures were
converted to support a variety of DOE research projects. Full-scale
decommissioning, decontamination and demolition of the TAN facilities began in
2005.
First up was the Loss-Of-Fluid-Test (LOFT) reactor facility. The 60,000-sq-ft
LOFT facility was a scale-model of a commercial pressurized-water reactor power
plant built chiefly to explore the effects of loss-of-coolant accidents
including core melt down. The steel dome was designed to safely contain such
accident scenarios. An 80-ton shielded locomotive originally intended to
transport the reactor-powered jet engines was employed to move the reactor in
and out of the containment dome by rail to the nearby Hot Shop facility for
maintenance and test modifications. The reactor itself had been removed in 1986.
Demolition of the rest of the 60,000-sq-ft LOFT facility, control room and other
support structures involved the use of various D&D techniques, including
explosives and heavy equipment processing.
By far the most complex part of D&D work at TAN was the Hot Shop complex. The
153,661-sq. ft. complex included the TAN-607 Hot Shop itself, at the north end
of the complex, as well as several support structures built on later. The
165-foot long, 55-foot high Hot Shop had 7-foot-thick reinforced concrete walls
that tapered to 2 feet thick at the top, two 5-foot-thick concrete doors, nine
6-foot thick viewing windows, and several remotely-operated cranes and
manipulators. Built onto the Hot Shop were other facilities, including several
smaller hot cells for more detailed work, an adjacent “warm shop” for staging
and other preparatory work, and a spent fuel storage basin that was drained and
closed in 2004. The massive facility also included a decontamination shop,
engine maintenance and large machine shops; high bay assembly shop; chemical
cleaning area and office areas on the second floor.
Demolition of the facilities proceeded from the south end of the complex,
using heavy equipment processors after all hazardous materials like asbestos and
lead had been removed from the structure. The Hot Shop itself presented an
enormous challenge, requiring three stages of complex explosive demolition to
bring it down. An initial test blast in one wall was used to confirm the
calculations of how much explosive would be required to break down the facility
walls. In the next phase, a series of archways were blasted into the walls of
the facility, and then the remaining portions of the walls were blasted in the
final phase to bring down the facility roof. From there, heavy equipment
processors were brought in to size the remaining debris. Throughout the process
multiple techniques were employed to control contamination. Contaminated debris
from the demolition was transported to the Idaho Site’s lined CERCLA disposal
facility. Remaining uncontaminated debris and other inert material was used as
backfill material. The building site and a nearby soil berm were then restored
to the natural grade level and seeded with native vegetation to close out the
project.
The team responsible for the TAN project maintained a strong safety record
throughout the project, completing it four years ahead of schedule and at a
significant cost savings. The funding cost and schedule savings related to the
TAN D&D work have enabled greater progress in other areas of the Idaho Cleanup
Project.
Editorial Date April 29, 2009
By Bradley Bugger
|